| 1975 to 1982 |
|
With National Electricity Board
(now Tenaga Nasional Nerhad) supervising the
construction of: |
|
. |
(1) Temengor Hydroelectric Dam
near Grik, Perak |
|
|
(2) Kenyir Hydroelectric Dam in
Ulu Trengganu |
|
|
(3) Pasir Gudang Power Station
in Johor |
|
. |
|
| 1982 |
|
As a Senior Engineer with Sabah Gas Industries in
the supervisison of the Sponge Iron Plant, Methanol
Plant and Power Plant at Ranca-Ranca Industrial Area in
Labuan, Sabah. Contractor used vibro-compaction
equipment to build stone columns as the foundation |
|
. |
|
| 1982 to 1984 |
. |
As a Project Manager with
McConnel Dowell Kelana Sdn Bhd in the construction of
Quay No. 1 and 2 for Malaysia Shipyard and Engineering
Sdn Bhd in Pasir Gudang, Johor. |
|
. |
|
| 1984 to 1988 |
|
As a subcontractor in the consruction of three (3)
minihydro power plants for National Electricity Board
at:- |
|
|
(1). Sungei Bil at Slim River in Perak |
|
|
(2). Sg. Kinjang at Tapah in
Perak |
|
|
(3). Sg. Kerling at Kerling in Selangor. |
|
. |
|
| 1988 to 1992 |
|
As a General Manager With the Renong Group in the Project
Management of the North-South Highway Project from
Bukit Kayu Hitam in Perlis to Johor Bahru in Johor.
Later when in Time Engineering Berhad, involved in the
tendering and construction of the 1.0 MW Bombalai
Minihydro Plant near Tawau in Sabah (East
Malaysia) |
|
. |
|
| 1992 to 1997 |
|
As a Director of With Bilfinger + Berger Civil
Construction Sdn Bhd in the construction of: |
|
|
(1) Oleochemical Plant for
Felda Procter & Gamble in Kuantan |
|
|
(2) Bulkhead for Penang Shipbuilding &
Construction Sdn Bhd at Pulau Jerejak in Penang |
|
|
(3) CSR Plant in Senawang, N.Sembilan |
|
|
(4) Wharf for Bina Puri Sdn Bhd at Miri, Sarawak -
design & construct |
|
. |
|
| 1999 to 2000 |
|
As a General Manager with The Malay Chamber of
Commerce in the Project Management of the
completion of 50 schools in Malaysia for the Ministry of
Education on design, build and negotiated
basis.
|
|
. |
|
| 2000 to 2004 |
|
As the Chief Resident Engineer with Wan Mohamed and
Khoo Sdn Bhd in association with CTI Engineering Ltd of
Japan and Asociated Consulting Engineers Co.Ltd of
Pakistan, for the supervision of the construction of the
Beris Dam for the Drainage and Irrigation Department of
Malaysia. |
|
|
|
| 2004 to Now |
|
Self-employed and assisting Wan Mohamed and Khoo Sdn
Bhd in the administration of the following contracts:
- |
|
|
(1) Contractual claims from the Beris Dam Project
(completed) |
|
|
(2) Land Reclamation Project at Bandar Hilir, Melaka for
the Ayer Keroh Resort Sdn Bhd, a subsidiary of the Lion's
Group (in progress) |
|
|
(3) Students Hostel at Kuala Trengganu for Yayasan Trengganu
(completed) |
|
|
(4) Upgrading of the Sg.Pong Minihydro Plant at
Klian Intan (preliminary stage) |
|
|
(5) Other projects under proposal stage |
|
|
|