.

                                                          
Construction Page
                                                                                                           

  Home  |  Construction   |   Infor.Technology  |  My Journal

Project Planning & Scheduling

Project Planning and Scheduling is related to Project Management. I define Project Management as the process of implementing a project so that it is completed within the time stipulated and the budget allocated and of the required standard of quality.

The stipulation of budget, completion time and standard of quality is determined by the engineering consultant with the aproval of the Owner of the project. The Project Management Team ensures that the wishes of the Client shall be respected and therefore endeavour to fulfill those wishes to the fullest.

The Beris Dam

View of the dam from downstream. The Spillway is on the right and the Valve House on the left.

.

It is regretted to note that due to certain weaknesses, which can be just one or a combination of many, most projects are not completed within the required budget and time. So, how does the Project Management Team ensure or avoid Cost Overruns and Delay in Completion? One of the answers is to have a proper and effective Project Planning and Scheduling tool. .

It is used to plan on what and when all the works are to be executed and completed, monitor the progress in terms of time and cost and take the necessary actions to catch up for any delay so that the project schedule is back to its original target of completion on a specified date.
.


Administration Building, Substation & Control Room

The above buildings are constructed as part of the Beris Dam Project


When monitoring the progress of the works, special attention is to be given to the Critical Path, which is defined as the time given to complete a critical task, without any allowance being given for any delay. The Project Manager must always ensure that the Critical Path is maintained to ensure that the target date of completion can be achieved.

What tools do we use to carry out Project Planning and Scheduling?

In the olden days, when computer technology was not so developed, the program of works was charted on a large piece of paper and every time there was a change in the schedule, the draughtsman had to change it manually. It is so time-consuming that it was difficult for the Client who stayed far away to monitor the progress of the project from his desk.

Nowadays, we have many types of computer programs to choose to plan and monitor the progress of works, such that the Client can get the latest information instantly. Thanks to internet facilities, he can even get the information "online" if he wishes.


The Twin Conduit Pipes and Valve House

The above structures form part of the Outlet Works in the Beris Dam Project


 

The choice of the tool depends on the nature of the project and how complex it is. When I was with the Dewan Perniagaan Melayu Malaysia (The Malay Chamber of Commerce), I was assigned to implement the project to design and construct a total of fifty (50) schools in the whole of Malaysia within two (2) years on a design-and-build basis. I used the Primavera as the Project Planning and Scheduling Tool to plan the programme of works and monitor the progress of each school. .

When I was at the Beris Dam Project in Kedah, I used the Microsoft Project 2000 to monitor the progress of works of the Contractor.

The tools not only helped me to monitor the progress of the works, it also helped me to establish the progress records, which were useful when it came to  evaluating and assessing  the claims submitted by the Contractor for extension of time.


For further enquiries or information, please write to roslan@roslank.com

or fill and send the mail form


 

Ir. Roslan Karimudin


Click on photo for a closeup view

My Resume


CONSTRUCTION



INFORMATION TECHNOLOGY



Mini-Hydro Development


.

For enquiries, please write to:

roslan@roslank.com

or send a mail form

or Call +6013-2020 998

or +6013-2020 787

.

Jubli Intan 65

.

 

 


.

In Planning & Scheduling, we don't want the project to be "under construction" all the time. We want to complete it within the stipulated time or earlier.

.
.

Use water available at the stream in the vicinity of your land to generate electricity 


.

Free Guestbook
My Guestbook  

 

 

 

 

 

 

 

 

This Web Page Created with PageBreeze Free HTML Editor